Project development has been going on for two years.
Somerset Wind was originally proposed by First Wind, the developer of the 62 turbine wind farm in Bingham. Somerset Wind was the next phase of a multi-part plan to develop a large cluster of wind farms in western Somerset and Franklin counties including the Moosehead Region
In 2015, First Wind was purchased by SunEdison, the world’s largest renewable energy developer. In April of 2016, SunEdison filed for bankruptcy after accumulating massive debt in a buying spree that included First Wind the Somerset Wind project. Through the bankruptcy divestiture process, the rights to Somerset Wind were sold to NRG, another major player in renewable energy development. NRG took possession of Somerset Wind in September of 2016.
From 2015 to 2017, preparations have been underway to complete a number of studies and evaluations necessary for Somerset Wind to initiate the permitting process with the Maine Department of Environmental Protection. At this time, we do not have a detailed status of those preparations, but we assume NRG is poised to submit a permit application once they secure a long-term (20 year) energy power purchase agreement.
During Somerset Wind’s transition of ownership, the State of Massachusetts was planning to release a request for proposal (RFP) for 9.5 million Mwh of renewable energy (wind/solar/hydroelectric) for delivery in 2020 to meet their renewable mandates set by the Massachusetts legislature. The Mass Clean Power RFP was released in March 0f 2017 – it called for bids to be submitted by July 27, 2017 with the expectation that successful bidders would be selected in January of 2018. Somerset Wind submitted a bid in July to supply 93.6 MW of wind power for 20 years to three utilities in Massachusetts.
In order to transport Somerset’s output to Massachusetts, they have partnered with Central Maine Power and their proposed Maine Clean Power Connection (MCPC) high voltage transmission line. The 145 mile MCPC line with run from the western border (west of Eustis) with Quebec to a substation at the base of Johnson Mountain, then down to Moscow, Pittsfield and connect in Westbrook to the line that eventually feeds power to southern New England. The Somerset county portion of the MCPC line will cut a 26.5 mile, 1400 foot wide corridor and cross through The Forks and span the Dead River. The MCPC will also be available to connect the proposed NextERa projects being planned in Alder Stream and Penobscot Townships. Combined, the NextERa projects will total 163 turbines.
In addition to the two NextEra projects, EDF, a Canadian company, is proposing Timberline Wind – a 43 turbine project that will also tie-into the MCPC transmission. The exact location of Timberline Wind was not disclosed in their bid to Massachusetts, but we hope to know the development site in a few weeks.
The future of Somerset Wind and the other four projects being proposed in the region rely exclusively on CMP’s MCPC line to connect them to Massachusetts. If the MCPC line is not a selected bidder (they submitted a separate bid), the proposed wind farms have no market access and would not meet the RFP requirements.
We will continue to update the Somerset project and the MCPC as information becomes available.